    1. Question:
    2. Answer:
    3. Additional Information
    4.  
    • Article Type: General
    • Product: Alma

    Question:

    How can I modify PO line (POL) allocation between funds? For example, I want to change the fund of POL to another fund.

    Answer:

    A POL set is required to run the Update PO Line Transactions.


    To create a POL set:

    1. Go to Admin > Manage Sets

    2. Click +Add Set and select "Logical".

    3. Enter the Set Name and select the content type "PO Line". The Status should be Active. Click the "Next" button.

    4. Enter the search criteria.

      • For example, Fund Code = X AND Workflow = Waiting for Renewal

    5. Once the results include only the POLs you would like to update, click the "Save" button.

    6. Click the "Save" button again when you are returned to the Set Details page.

     

    The POL set is now saved and ready to be used in the Update PO Line Transactions job.

     

    To run the Update PO Line Transactions job:

    1. Go to Admin > Run a Job

    2. Search for the "Update PO Lines transactions" job. Select the job and click the "Next" button.

    3. Select your POL set and click the "Next" button.

    4. Enter the parameters, then click the "Next" button.

      • For example, select the preferred Fund and enter the Percent as 100.

    5. Confirm the details are correct, then click "Submit."

     

    The job will now run. Once complete, view the Job Report by clicking on the name of the job where it appears in Admin > Monitor Jobs > History tab.

    Please note: When you don't add a percentage when handling one fund the job will fail with error "Funding list contains invalid values".

     

    Additional Information


    For additional information about creating POL sets and making bulk changes to POLs, see:

    Creating an Advanced Search for PO Line Sets

    Performing Global Changes on PO Line Sets

    Changing Vendors in PO Lines and POs


    Article last edited: 29-MAY-2018

     

    View article in the Exlibris Knowledge Center
    1. Back to top
      • How to run the SIS loader manually
      • How Do Scheduled Jobs Work in Alma?
    • Was this article helpful?

    Recommended articles

    1. Article type
      Topic
      Content Type
      Documentation
      Language
      English
      Product
      Alma
    2. Tags
      This page has no tags.
    1. © Copyright 2025 Ex Libris Knowledge Center
    2. Powered by CXone Expert ®
    • Term of Use
    • Privacy Policy
    • Contact Us
    2025 Ex Libris. All rights reserved