Desired Outcome Goal:
I have run the Acquisitions year end steps and had a mistake in one of the steps.
I have run the following in this order:
Open Annual Budget (acq-05)b-acq-06-a
Renew Order Encumbrance for Monograph (acq-06-a)
Renew Order Encumbrances for Serials and Standing Orders (acq-06-b)
Transfer Remaining Balance (acq-07)
By mistake I ran "Renew Order Encumbrances for Serials and Standing Orders (acq-06-b)" with Update Database = No.
Is it possible to rerun this with Update Database = Yes if we have already run "Transfer Remaining Balance (acq-07)"?
Procedure:
Yes, that's possible. Just run "Renew Order Encumbrances for Serials and Standing Orders (acq-06-b)" with Update Database = Yes.