Can we run Global Data Change (GDC) jobs and BulkImport jobs simultaneously?
Answer
You should avoid running GDC and BulkImport jobs simultaneously, as both processes can be resource-intensive, and issues may arise if both processes attempt to update/overlay the same record(s).
Additional Information
See Global Data Change Document, "IMPORTANT - Before You Begin" section, which covers system prerequisites, best practices and other considerations for planning data changes.