Can the 4th and 5th reporting codes be updated via the "Update PO Lines Information" job?
Question
Can the Alma "Update PO Lines Information" job update all "Reporting Codes", in batch?
Answer
Yes, all Reporting Codes can be updated by the Job. Originally, only the 1st, 2nd and 3rd Reporting Codes were included in this job. Now, also the 4th and 5th Reporting Codes can be updated in bulk, through an Order Lines Set.
Question
Read more about the "Update PO Lines Information" job and others, here.